Cody Colt, City of Yelm public services director, and Brad Chatwood, City of Yelm projects and programs manager, made it clear during a Yelm City Council study session meeting on Tuesday, Feb. 3, that their department will be jam-packed with projects this year.
Colt clarified that all of the mentioned projects are either happening right now or will happen within the year’s timespan. Additionally, he told council he’d be providing information on where the project is at in the process, what pricing looks like and why some projects may be delayed.
Water Reclamation Facility
Colt first discussed the City of Yelm’s Water Reclamation Facility (WRF) — which has been an ongoing project since 2017 when council voted to adopt sewer rates. With that adoption, it led to the city’s interest in constructing the WRF.
Colt noted that Yelm received approval from the Department of Ecology to begin the project in 2021.
“It’s been being built for the last five years and we’re finally at the culmination. It should be finished this year,” Colt said. “We’re actually starting a solids side, turning them on, part of the solids side project, in about two months. That’s the last little phase of this project.”
He added that the City of Yelm received a loan from the Department of Ecology worth roughly $36 million for the WRF project. Additionally, Yelm will begin to repay the loan in 2027.
“The benefit of council adopting the rates in 2017, we didn’t have to increase rates to do this. Sewer rates auto-increase with CPI every year, but because of that, we haven’t had to go back to council for a rate adjustment — which has been huge,” Colt said. “We just had a meeting with another city today where they’re exploring building another plant, and their rates will have to go up significantly. 10 to 20% more.”
Colt added that the City of Yelm has also finished a sewer rate study to see if rates can either be lowered or kept around the same.
“I’m happy to report we can at least keep rates the same,” Colt said. “Lowering may not be able to happen until the 2029 budget. I’m still crunching the numbers right now. The good news is we don’t have to increase rates as loan payments start. We’ll probably relook at rates in the 29-30 budget and lower them, possibly, on the sewer side of things.”
Chatwood noted that the public services department is getting ready to “fire off” some of the solid waste within the WRF. Additionally, he said that liquid waste within the facility is “99% there.”
“Everything is running great,” Chatwood said. “We’ve had our hiccups but we’re getting there.”
Cochrane Memorial Park Phase 2
Colt first highlighted the proposed upgrades to Yelm’s Cochrane Memorial Park, located at 750 Mill Road SE. He stated the City of Yelm has been discussing Phase 2 of the Cochrane Memorial Park upgrades “forever.”
He noted that Phase 1 of the Cochrane Memorial Park added the park’s front pond and introduced giant reed grass to suck up nitrogen and purify the water.
“We wanted to do the back half of Cochrane Park at the same time, but ecology said ‘no, you have to go through this whole entire study.’ We finished the study,” Colt said. “The hope is ecology, now, will let us go ahead and upgrade phase two — which means the back half of the park.”
Additionally, Colt said some lighted water fountains would be implemented into the big duck pond near the dock at the park. The dock itself would also be redone, and a pavilion would be constructed.
“You could host weddings at it and have different events, baby showers, whatever. That’s phase two,” Colt said. “We have to wait for ecology to give us the ok because there’s some permitting stuff with the water going into the ground. The benefit is we’ve been doing testing over the last year and it’s showing the water we’re putting into the ground is better than the aquifer water that’s in the ground. We’re actually making the water more clean.”
According to Colt, Yelm Public Services is hopeful to begin working on this project in 2026. He noted that plans for the project are complete, and Yelm just awaits approval from the Department of Ecology.
“In Phase 2, we’re going to enlarge those two big ponds over on the Mill Road side, which I think we’ll lose a tree or two there,” Colt said. “The pavilion will take down a single tree. The one tree that’s leaning really bad on the back half, which is about to fall on the pond, will probably come out too.”
Yelm Prairie Line Trail Phase 2B
Colt stated that Phase 2B of the Yelm Prairie Line Trail project was expected to be completed in December, but noted that several slabs came in “out of specs” and caused puddling on the pathway across the trestle over the Nisqually River.
“A lot of these concrete slabs got rejected and we have to replace them, but I believe we’re good now,” Colt said.
Chatwood added that 11 total slabs were rejected and needed replacement on the trail. The replacements came at zero cost to the City of Yelm.
The trestle portion of the trail, which spans across the Nisqually River, is also rated for tonnage, according to Chatwood.